Demolition of existing and construction of new fish market on Shetland
About Project
This project was awarded to CHAP Group (Aberdeen) Ltd in October 2018.
Works started on site in December 2018 and reached completion in December 2019 – some 3 months ahead of schedule.
The original Scalloway fish market, which was built in the 1970’s and refurbished and extended in the 1990s, was demolished and replaced with a state-of-the-art building.
A new facility was desperately needed as the amount of fish being landed rose by 600% between 2004 and 2015. Vessels were often turned away and were unable to land their catch due to lack of capacity.
The works included:
Construction of a steel framed building with welfare facilities
Construction of three chilled compartments with transport corridor
Construction of lorry loading bays
Construction and surfacing of yard area and deck slab
Retaining walls
Full installation of lighting, electrical services and all plumbing and water connections